← All stories

1954–1967

How the Bratsk dam was built.

Two river closures, first generators and final commissioning were distinct stages of one construction project.

01

First, the means to build

The project was approved in September 1954. Roads, housing, production bases and an external power supply were needed before generation could begin. A line from Irkutsk initially powered construction.

1 March 1961. Bratsk hydroelectric station on the Angara.
1961

The construction site in 1961

1 March 1961. Bratsk hydroelectric station on the Angara.

Валерий Шустов / Valeriy Shustov · Wikimedia Commons / РИА Новости
CC BY-SA 3.0 · Original ↗

02

Two closures of the Angara

On 30 March 1957, the right-bank channel was closed from the ice to form the construction pit. The final closure followed on 19 June 1959, routing water through temporary dam openings. Excavation and the first foundation concrete of 1958 lay between them.

1 October 1960. Bratsk dam under construction.
1960

Autumn at the construction site

1 October 1960. Bratsk dam under construction.

Алексей Бушкин / Alexey Bushkin · Wikimedia Commons / РИА Новости
CC BY-SA 3.0 · Original ↗

03

Power before final commissioning

The first unit supplied power on 28 November 1961. Installation, construction and controls continued: the central control room opened in 1964 and the last unit came under load on 14 December 1966. The complex was accepted on 8 September 1967.

1 March 1961. Equipment installation at Bratsk dam.
1961

Hydroelectric equipment

1 March 1961. Equipment installation at Bratsk dam.

Валерий Шустов / Valeriy Shustov · Wikimedia Commons / РИА Новости
CC BY-SA 3.0 · Original ↗

04

The dam as a route

Trains and road vehicles crossed the crest in 1965, making the dam part of the city’s transport system. The 1960–1961 photographs show the earlier construction phase.

7 April 2016. Train on the dam crest. A later photograph of equipment and structures, rather than a construction-era image.
2016

Train on the dam crest

7 April 2016. Train on the dam crest. A later photograph of equipment and structures, rather than a construction-era image.

Сайга · Wikimedia Commons
CC BY-SA 4.0 · Original ↗

05

Inside the hydroelectric complex

Generating units stand in the machine hall, where a crane moves heavy components during installation and maintenance. Turbines use water flow and generators convert mechanical work into electricity. Electrical equipment and a network carry that power to consumers.

The detailed HPP history has 32 chapters on surveys, foundation pits, winter concrete, resettlement, equipment and commissioning. The machinery photographs in this article were taken in 2016.

7 April 2016. Machine hall. A later photograph of equipment and structures, rather than a construction-era image.
2016

Machine hall

7 April 2016. Machine hall. A later photograph of equipment and structures, rather than a construction-era image.

Сайга · Wikimedia Commons
CC BY-SA 4.0 · Original ↗

7 April 2016. A generating unit. A later photograph of equipment and structures, rather than a construction-era image.
2016

A generating unit

7 April 2016. A generating unit. A later photograph of equipment and structures, rather than a construction-era image.

Сайга · Wikimedia Commons
CC BY-SA 4.0 · Original ↗

Sources for this story

  1. Bratsk dam: construction stages ↗
  2. Commissioning the Bratsk hydroelectric station ↗
  3. Chronicle, 1954–1963 ↗

Photographic records

1 March 1960. Building the Bratsk dam.
1 March 1960. Building the Bratsk dam.
Макс Альперт / Max Alpert · CC BY-SA 3.0 · Original ↗
7 April 2016. A generating-unit model. A later photograph of equipment and structures, rather than a construction-era image.
7 April 2016. A generating-unit model. A later photograph of equipment and structures, rather than a construction-era image.
Сайга · CC BY-SA 4.0 · Original ↗
7 April 2016. Generator. A later photograph of equipment and structures, rather than a construction-era image.
7 April 2016. Generator. A later photograph of equipment and structures, rather than a construction-era image.
Сайга · CC BY-SA 4.0 · Original ↗
7 April 2016. Machine-hall crane. A later photograph of equipment and structures, rather than a construction-era image.
7 April 2016. Machine-hall crane. A later photograph of equipment and structures, rather than a construction-era image.
Сайга · CC BY-SA 4.0 · Original ↗

Eyewitness voices

A legend of our time ↗ 2014 / 15:32

Viktor Kirichenko remembers Bratskgesstroy ↗ 2019 / 03:58

Later interviews and films about events before 1991.

Dates in this story

Industry

The decision to build the dam

The Bratsk hydroelectric project is approved. Managers, machinery and workers arrive, while housing and roads must be built alongside the works.

Read the full story ↗
Industry

A closure from the ice

The right-bank channel is closed from the ice to create a construction pit. This is distinct from the final closure of the Angara in 1959.

Read the full story ↗
Industry

Concrete for the dam foundation

The first concrete is laid in the dam foundation as preparatory work gives way to the main structures.

Read the full story ↗
Industry

The Angara’s final closure

The river is diverted through temporary openings in the dam, a different engineering stage from the ice operation of March 1957.

Read the full story ↗
Industry

The Angara generates power

The first generator delivers electricity. Filling the reservoir transforms the Angara landscape and the lives of riverside communities.

Read the full story ↗
Industry

Trains cross the dam

Freight and passenger trains cross the crest, making the dam part of the transport connection between the banks.

Read the full story ↗
Industry

The eighteenth unit

The final generating unit comes under load. Permanent commissioning of the complete complex follows in 1967.

Read the full story ↗
Industry

The station is commissioned

The Bratsk hydroelectric complex enters permanent operation, then the world’s largest hydroelectric station.

Read the full story ↗